This instruction show you guide on how to do insulation testing for Still RX20 forklift electric trucks.More topics about Still trucks,please refer to:Still Forklift Repair
Related Contents:(all workshop manual included in below software)
STILL STEDS Forklift 8.19 8.18 2019 EPC & Diagnostics Free Download
Insulation testing must be carried out on the entire truck at least once a year as part of the FEM test.Insulation testing must also be carried out after any work on the electrical system or repairs to the electrical system.
Insufficient insulation values in the truck can lead to undefined errors that are not reliably detected in the diagnostic process.
This test measures the insulation of the entire truck.
If insufficient measured values are obtained, the insulation must be measured for the following components to ensure that no errors are present: